Grand View-Semouha


Semouha-Alexandria

Location:
Semouha-Alexandria

Client:
Alexandria Company for the Reconstruction and Development of tourism

Scope of Works:
• Diaphragm Wall Works
Construct anchored diaphragm walls with thickness from 640 mm and depth of walls 29 meters. Total quantity of executed diaphragm wall is 20,350 square meter.


• Soft Gel Grout Plug Works
Grout a soft gel plug at a depth of 29 meter from the street level. Plug thickness 2 meter. Grouted area is 21,000 square meter.

Groundwater Control System
Bauer Egypt was responsible for the supply and installation of complete groundwater control system comprising 28 deep wells, piping works and alarm system. The controlling system is expected to run for about 16 months after completion of the soft gel grout plugs.


• Tension piles
Construct of about 630 no. of bored pile with diameter 600 mm and depth 20 m.


• Ground Anchor
Construct of about 1,210 no. of anchor with average length 20 m